Skip to main content

I want to be PMP, Where do I start?

I was called for an interview and I was told to get PMP certified.
My company is asking for 10% of managers to be PMP certified by this year.
Leadership role requires everyone to be PMP certified so I need to get PMP certification.
Many situations arise and you wonder, is it time to start preparing for PMP?

Where to start, Where are all PMP resources

The question is - Where to start, Where are all PMP resources and get the best PMP knowledge so that I Pass PMP in my First attempt or I pass PMP within a month.
First thing first:
You need to check a website:
http://www.pmi.org/
Why?
beacuse PMI is the one organization, based in USA which will award you with PMP certification. PMI holds the rights to PMP and few more certifications. we will talk about other certifications as well but in my next newsletter.
Now we know that PMI awards PMP certification. Great.
How do I start, well first of all check if you are eligible for PMP exam or not.

PMP eligibility criteria

PMP eligibility criteria can be checked here:
https://www.pmi.org/certifications/types/project-management-pmp
In a nutshell, PMP prerequisite is that you should have 16 Years of education and 3.5 years of role in which you are managing Projects. Understand that this is role which we are talking about and not designation.
So you could be an engineer but if you are doing projects then you are eligible. ( Understand that projects are not operations, however also understand that if you are in operation role you would have updated processes, or technology or implemented any change. A project is unique and has a start date and end date) so operations carry projects. so you need to think of instances where you created something unique and calculate if it is more than 3.5 years.
Hmm now, that's sorted. You would also need to undergo a formal PMP training which will award you with 35 PDU certificate. All these 3 things, Education, Project Management Experience and Project Management formal education is the pre-requisite to apply for PMP exam.



Popular posts from this blog

Risk and Risk response questions in PMP and RMP

Here is another question posted by one of the participant:



Hi Kavita... one more query...regarding Risk Response Plan. If I find a risk of missing deadline...and to avoid that I work extra time or hire few temp contractors to complete the work within deadline. So is this case of AVOID risk or ACCEPT risk? I did avoided the risk by adding more time/resources. However I also accepted that risk will occur and hence hired more people. From what I understand is ACCEPT is you don't take any action and wait for the risk to happen and use contingency plan. So in that case I accepted risk and my contingency plan was to hire more people. But at the same time AVOID risk says, take action and eliminate risk. So I eliminated risk by hiring people. just too much confusion :)
So what is the answer to above question?This is what I posted back..
A risk has some probability and some impact - I'm sure you know that.. Now lets understand the risk responses in detail: Accept - Do Nothing Avoid - Sele…

Critical Path Method (CPM) Simplified..

A critical path is the longest path in the network.  Each node which falls under critical path has zero or negative float (Slack).
Now how do we calculate critical path?? I’ve seen various illustrations having different way to calculate CPM, few are:
-The project starts on day 1. -The project starts on day 0.
Both the approaches give same results, however I liked the day 0 approach better, its simpler, easy and lesser room for errors.
Example
 There are 3 steps to calculate CPM: 1. Forward Pass - To calculate the Early Start(ES) and Early Finish(EF) of node. 2. Backward Pass - To calculate Late Start (LS) and Late Finish(LF) of node. 3. Calculate Float and Thus CPM.
The Forward Pass: We start from first Node or Start node. The works begin on day 0. 
We’ll fill up information in highlighted boxes:
In forward pass, we calculate the Early Start and early finish date of activities.
Node A: The activity starts on day zero, since A activity duration is for 5 days, the early finish…