Skip to main content

Is PMP difficult to Pass?

I was in a PMP workshop (PMP Preparation). It was for an organisation and in-house.
Good, matured project managers from various streams including finance, operations and training domain were in the room.
This was Day 1. People were all tensed up, and you could sense the tension in the atmosphere.
I started with joke and a few activities before lunch and slowly people got relaxed.
The next day - again same environment, the folks went back and opened PMBOK and felt very nervous and hence the anxiety in environment.
Someone asked "Why should I sit for the examination - what are the advantages of being a PMP"? 
Is this a question for Day 2?? I wanted to ask, "You tell me why are you in this workshop - what made you decide to spend your money and be part of this session?"
But I guess that was just the anxiety speaking.
The same person on Day 4 (Last day) came back and said : "I went through PMBOK and I felt like I can read this book and understand the book.." (with a grin on his face).
That was the reward of spending 4 intensive days with the participants. 
I'm sure that within 30 days I will get many mails of thanks once this batch starts appearing for the examination. 
So the question - Is PMP a difficult exam to pass? 
Yes and No, Now I understand that this is not an answer :) but you need to understand what is expected from you for being a PMP.
Understand small things like:
  • Type of question
  • Pattern of questions
  • Important Topics
  • Knowledge area and process group importance 
Few tricks can also help in answering a typical PMP question, but above all - You would need to start with the basics.
If someone can put a simple picture together of the overall project management processes and the correct picture, then you are off to a great start. Thats what I would recommend - Start with the basics - get them clarified and then practice as much question as you can. And, within 3-6 weeks you will be proud to showcase your PMP Badge.
Happy Learning...

Popular posts from this blog

Risk and Risk response questions in PMP and RMP

Here is another question posted by one of the participant:



Hi Kavita... one more query...regarding Risk Response Plan. If I find a risk of missing deadline...and to avoid that I work extra time or hire few temp contractors to complete the work within deadline. So is this case of AVOID risk or ACCEPT risk? I did avoided the risk by adding more time/resources. However I also accepted that risk will occur and hence hired more people. From what I understand is ACCEPT is you don't take any action and wait for the risk to happen and use contingency plan. So in that case I accepted risk and my contingency plan was to hire more people. But at the same time AVOID risk says, take action and eliminate risk. So I eliminated risk by hiring people. just too much confusion :)
So what is the answer to above question?This is what I posted back..
A risk has some probability and some impact - I'm sure you know that.. Now lets understand the risk responses in detail: Accept - Do Nothing Avoid - Sele…

Critical Path Method (CPM) Simplified..

A critical path is the longest path in the network.  Each node which falls under critical path has zero or negative float (Slack).
Now how do we calculate critical path?? I’ve seen various illustrations having different way to calculate CPM, few are:
-The project starts on day 1. -The project starts on day 0.
Both the approaches give same results, however I liked the day 0 approach better, its simpler, easy and lesser room for errors.
Example
 There are 3 steps to calculate CPM: 1. Forward Pass - To calculate the Early Start(ES) and Early Finish(EF) of node. 2. Backward Pass - To calculate Late Start (LS) and Late Finish(LF) of node. 3. Calculate Float and Thus CPM.
The Forward Pass: We start from first Node or Start node. The works begin on day 0. 
We’ll fill up information in highlighted boxes:
In forward pass, we calculate the Early Start and early finish date of activities.
Node A: The activity starts on day zero, since A activity duration is for 5 days, the early finish…